Monthly Progress Report
In Construction projects, Contractor needs to submit a Monthly Progress Report to the Engineer with the Work progress well describe. Normally a monthly progress report will consist of the project details, physical work progress, financial progress, resource availability, other concerns related to project progress, photos to prove monthly work done, etc. The planning engineer/ quantity surveyor of the project is preparing the report under the guidance of the project manager. Monthly progress report will be the basis for the evaluation of monthly payment certificates in general.
A Sample Monthly Progress report is given below.
MONTHLY REPORT
FOR THE MONTH OF
JULY 2018
PROJECT PICTURE/ COVER
ANY OTHER
DATE OF SUBMSSION
------------------------------------------------------------------------------------------------------------------------
Monthly Progress Report Jan 2020
Table of Contents
1.
|
INTRODUCTION............................................................................................................
|
4
|
||
1.1.
|
Project
Description ....................................................................................................
|
4
|
||
1.2.
|
Contract
Data of the Project ....................................................................................
|
5
|
||
1.3.
|
General
Description Of Monthly Progress .............................................................
|
6
|
||
2.
|
PROJECT
DETAILS ......................................................................................................
|
7
|
||
2.1
|
Completion
Dates for Major Activities ...................................................................
|
7
|
||
2.2
|
Project
Organization ...............................................................................................
|
10
|
||
2.3
|
Construction
Programme .......................................................................................
|
11
|
||
3.
|
PHYSICAL
PROGRESS ..............................................................................................
|
12
|
||
3.1.
|
Work Done
for Dec 2019........................................................................................
|
12
|
||
3.2.
|
Planned Work
for Jan 2020 ..................................................................................
|
15
|
||
3.3.
|
Progress
Photographs .............................................................................................
|
15
|
||
4.
|
FINANCIAL
PROGRESS ............................................................................................
|
16
|
||
4.1.
|
Status of
Financial Progress ...................................................................................
|
16
|
||
4.2.
|
Summary of
Actual Work Done up to End of 2019 ....................................
|
17
|
||
4.3.
|
Physical Progress of Planned
Work & Actual Work According to Cash Flow17
|
|||
4.4.
|
Notice of
Claim ........................................................................................................
|
17
|
||
4.5.
|
Variation
Orders .....................................................................................................
|
17
|
||
5.
|
QUALITY ASSURANCE AND QUALITY
CONTROL...........................................
|
18
|
||
5.1
|
Project
Quality Plan ................................................................................................
|
18
|
||
5.2
|
Request for
Information – RFI ..............................................................................
|
18
|
||
5.3
|
Shop Drawing
Register ...........................................................................................
|
18
|
||
5.4
|
Design
Report Register ...........................................................................................
|
18
|
||
5.5
|
Method
Statement Register ....................................................................................
|
18
|
||
5.6
|
Contractor’s
General Submissions – CGS ............................................................
|
18
|
||
5.7
|
Contractor’s
Material Submissions – CMS ..........................................................
|
18
|
||
5.8
|
Summary of
Concrete Casting ...............................................................................
|
18
|
||
5.9
|
Summary of
Deliveries of Rebar ............................................................................
|
19
|
||
5.10 Summary of Concrete Trial Mix Test
Results ..................................................
|
19
|
|||
5.11
|
RICF Register ......................................................................................................
|
19
|
||
5.12
|
NCR Register .......................................................................................................
|
19
|
||
5.13
|
Bar Schedule Register .........................................................................................
|
19
|
||
6.
|
HEALTH, SAFETY, ENVIRONMENTAL
AND SECURITY.................................
|
20
|
||
6.1
|
Health &
Safety Key Performance Indicators ......................................................
|
20
|
||
6.2
|
Health .......................................................................................................................
|
21
| ||
6.3
|
Safety ........................................................................................................................
|
22
|
|
6.4
|
Environment ............................................................................................................
|
22
|
|
6.5
|
Security .....................................................................................................................
|
23
|
|
7.
|
CONTRACTOR'S
RESOURCES...............................................................................
|
24
|
|
7.1. Summary of Manpower Allocation .......................................................................
|
24
|
||
7.2. Summary of Machinery Allocation .......................................................................
|
25
|
||
8.
|
Weather
Record .............................................................................................................
|
26
|
|
9. SITE AND OTHER MATTERS...................................................................................
|
26
|
||
9.1
|
Diary of
Major Incidents During the Period ........................................................
|
26
|
|
9.2
|
Problems
& Difficulties Encountered During the Period ....................................
|
26
|
|
9.3
|
Pending
Matters ......................................................................................................
|
26
|
|
10.
|
LEED REPORT..........................................................................................................
|
26
|
|
List of Tables
| |||
Table 1: Contract data of the
project
.......................................................................................
|
5
| ||
Table 2: Completion dates for
major activities
........................................................................
|
7
| ||
Table 3: Foreign Personnel
......................................................................................................
|
10
| ||
Table 4: Local Perosonnel
.......................................................................................................
|
11
| ||
Table 5: DTP submission detail
...............................................................................................
|
11
| ||
Table 6: Planned and actual
excavation progress
....................................................................
|
12
| ||
Table 7: Planned and actual
D-wall hacking & capping beam casting progress .....................
|
14
| ||
Table 8: Status of financial
progress Dec 2019 .......................................................................
|
16
| ||
Table 9: Summary of actual
work done up to end of June 2018
.............................................
|
17
| ||
Table 10: Summary of Project
Quality Plan submission
.........................................................
|
18
| ||
Table 11: Health and safety
key performance indicators .........................................................
|
20
| ||
Table 12: Anti-mosquito
treatment summary table .................................................................
|
21
| ||
Table 13: Monthly summary of mosquito breeding
control ....................................................
|
21
|
List of Figures
| |
Figure 1: Location of Site ..........................................................................................................
|
4
|
Figure 2: Planned and actual excavation progress ...................................................................
|
13
|
Figure 3: Planned and actual Capping Beam Casting &
D-wall Hacking Progress ................
|
15
|
ANNEXTURES
Appendix
A: Progress updated programme detailed time programme for July 2018
Appendix
B: Programme for next month (August 2018)
1.
INTRODUCTION
1.1. Project Description
The …………… Commercial Development project located at ……….. consist of 60 –
story office building. It was invested by ……………. (Pvt.) Limited
and was designed by …………………… Consultants (Pvt.) Ltd.
Figure
1: Location of Site
The project covers an area of …….. square meters
and has a total building height of ………… meters. It is a super high-rise
building. The podium building has a gross floor area of approximately ………..
square meters and the tower gross floor area is approximately 57000 square
meters with a total gross floor area of ………. square meters.
1.2. Contract Data of the Project
Contract
data of the project is given in the following table.
Table 1: Contract data of the project
|
||
Contract
Name
|
:
|
|
Contract
No
|
:
|
|
Contract
Sum
|
:
|
|
The
Employer
|
:
|
|
The
Engineer
|
:
|
|
Project
Architect
|
:
|
|
Civil
and Structural Engineer
|
:
|
|
Services
Engineer
|
:
|
|
Quantity
Surveyor
|
:
|
|
Amounts
of Performance bond
|
:
|
|
The Contractor
|
:
|
|
Date of
Commencement
|
:
|
|
Scheduled
date of completion
|
:
|
|
Bonus
Entitlement Requirement
|
:
|
|
Minimum
Amount of Interim
|
:
|
|
Payment
Certificate
|
||
Environmental
Management and
|
:
|
Environmental
Plan and Safety Plan to be prepared and
|
Safety
Plan
|
monitored
throughout the construction period to avoid the
|
|
environmental pollution
in order to
satisfy LEED
|
||
requirements
and to ensure the safety of all the workers and
|
||
the
officer engaged in the project.
|
||
Quality
Assurance and Management
|
:
|
To ensure
the quality of works, proper Quality Management
|
Plan
|
Plan
prepared by the contractor in accordance with ISO
|
|
9001:2008
series has to be implemented on the Engineer’s
|
||
approval.
|
||
1.3. General Description of Monthly Progress
This report consists of monthly progress details of
the project Main Contract Works to proposed ………………. for the period starting
from …………
Summary of construction activities carried out
during the reporting periods are as follows:
Tower Construction
Top Soil excavation and disposal Deep excavation in center area
Dewatering and instrumentation and monitoring Capping beam rebar works
Diaphragm
wall hacking
General works and Temporary Site facilities
Construction of sanitary facilities, contractor’s site office, temporary
rebar yard for capping beam rebar works and boundary wall was on progress
Surveying
Works - Regular Surveying works were carried out at site
2. PROJECT
DETAILS
2.1 Completion Dates for Major Activities
Completion dates for major activities according to Detailed Time
Program Rev 0.2 are given in the following table.
Table 2: Completion dates for major
activities
No
|
Task Name
|
Duration
|
Start
|
Finish
|
1.0
|
Mobilization & Facilities ‐
Main Contractor
|
650 days
|
28‐Mar‐18
|
06‐Jan‐20
|
2.0
|
Engineering
|
840 days
|
28‐Mar‐18
|
14‐Jul‐20
|
2.1
|
Method Statement &
Inspection Test Plans
|
504 days
|
28‐Mar‐18
|
13‐Aug‐19
|
2.2
|
Shop Drawings
|
784 days
|
23‐May‐18
|
14‐Jul‐20
|
2.2.1
|
Structural
|
727 days
|
23‐May‐18
|
18‐May‐20
|
2.2.2
|
Architectural
|
686 days
|
29‐Aug‐18
|
14‐Jul‐20
|
2.2.3
|
M&E
|
686 days
|
29‐Aug‐18
|
14‐Jul‐20
|
3.0
|
Procurement
|
869 days
|
31‐May‐18
|
15‐Oct‐20
|
3.1
|
Structural
|
600 days
|
31‐May‐18
|
20‐Jan‐20
|
3.2
|
Architectural
|
600 days
|
24‐Feb‐19
|
15‐Oct‐20
|
3.3
|
M&E
|
600 days
|
24‐Feb‐19
|
15‐Oct‐20
|
4.0
|
OFFICE TOWER
|
1096 days
|
28‐Mar‐18
|
27‐Mar‐21
|
4.1
|
Tower Crane & Passenger
Hoists
|
187 days
|
31‐Oct‐18
|
05‐May‐19
|
4.2
|
Prerequisite Approvals
|
93 days
|
28‐Mar‐18
|
28‐Jun‐18
|
4.3
|
Substructure Works Tower
|
340 days
|
16‐May‐18
|
20‐Apr‐19
|
4.3.1
|
Excavation & Earth Works
|
220 days
|
16‐May‐18
|
21‐Dec‐18
|
4.3.2
|
Tower Area
|
211 days
|
08‐Aug‐18
|
06‐Mar‐19
|
4.3.3
|
Tower Podium
|
228 days
|
05‐Sep‐18
|
20‐Apr‐19
|
4.4
|
Super Structure
|
475 days
|
07‐Mar‐19
|
23‐Jun‐20
|
4.4.1
|
LOW ZONE
|
287 days
|
07‐Mar‐19
|
18‐Dec‐19
|
4.4.2
|
HIGH ZONE
|
191 days
|
16‐Dec‐19
|
23‐Jun‐20
|
4.5
|
Tower Architecture, MEP & ID works
|
646 days
|
25‐Apr‐19
|
29‐Jan‐21
|
4.5.1
|
LOW ZONE
|
503 days
|
25‐Apr‐19
|
08‐Sep‐20
|
4.5.2
|
HIGH ZONE
|
353 days
|
02‐Feb‐20
|
19‐Jan‐21
|
4.5.3
|
PH Elevation
|
96 days
|
26‐Oct‐20
|
29‐Jan‐21
|
4.6
|
Building Envelop
|
539 days
|
24‐Jul‐19
|
12‐Jan‐21
|
4.6.1
|
Elevation 1,3 & 4
|
439 days
|
24‐Jul‐19
|
04‐Oct‐20
|
4.6.2
|
Elevation 2 (PH Elevation)
|
80 days
|
25‐Oct‐20
|
12‐Jan‐21
|
4.7
|
Lifts & Escalators
|
247 days
|
18‐Apr‐20
|
20‐Dec‐20
|
4.8
|
Staircases
|
210 days
|
18‐Mar‐20
|
13‐Oct‐20
|
4.9
|
Signage
|
345 days
|
17‐Feb‐20
|
26‐Jan‐21
|
4.10
|
BMU
|
150 days
|
24‐Jun‐20
|
20‐Nov‐20
|
4.11
|
Landscape
|
100 days
|
28‐Sep‐20
|
05‐Jan‐21
|
4.12
|
Fire Fighting System
|
200 days
|
04‐Jul‐20
|
19‐Jan‐21
|
4.13
|
BMS
|
350 days
|
13‐Nov‐19
|
27‐Oct‐20
|
4.14
|
IT Works
|
350 days
|
13‐Nov‐19
|
27‐Oct‐20
|
4.15
|
Dismantle Construction Aids
|
42 days
|
05‐Oct‐20
|
15‐Nov‐20
|
2.2 Project Organization
Contractor’s project personnel are given in the following table.
Contractor's
Project Personnel
Position
|
Name
|
Remarks
|
|
Project
Manager
|
|||
Dept
Project Manager
|
|||
Dept
Project Manager
|
TBA
|
||
Commercial
Manager
|
|||
Chief
Engineer
|
|||
HSE
Director
|
|||
Admin
Manager
|
|||
QS
Manager
|
|||
Quantity
Surveyor
|
|||
Procurement
officer
|
|||
Finance
Dept Manager
|
|||
Finance
Dept Assistant
|
|||
M&E
Manager
|
TBA
|
||
M&E
engineer
|
|||
Chief Surveyor
|
|||
Surveyor
|
|||
ID
Manager
|
TBA
|
||
Material
Department Manager
|
|||
Construction
Dept Manager
|
|||
Site
Engineer
|
|||
QA/QC
|
|||
Site
Engineer
|
|||
Site
Engineer
|
|||
HSE
Manager
|
2.3 Construction Programme
Detailed Time Programme has been submitted for review and consent.
Detailed Time Programme submission details are given in following table.
Table 5: DTP submission detail
No.
|
Version
|
Ref. No
|
Submitted date
|
Status
|
Date
|
|||||||||
01
|
Detailed Time
|
02-May-2019
|
Revise &
|
|||||||||||
Programme Rev 0
|
Resubmit
|
|||||||||||||
3.
PHYSICAL
PROGRESS
3.1. Work
Done for Dec 2019 Excavation and Earth Works
Top Soil excavation up to 0.5m, deep excavation in
center area and disposal along with dewatering was carried out during the
reporting period. Detail of planned and actual excavation progress is given in
following table.
Table 6: Planned and actual excavation
progress
…………………...
………………….
………………….
…………………...
………………….
………………….
Comments