Skip to main content

SAMPLE MONTHLY PROGRESS REPORT

Monthly Progress Report



In Construction projects, Contractor needs to submit a Monthly Progress Report to the Engineer with the Work progress well describe. Normally a monthly progress report will consist of the project details, physical work progress, financial progress, resource availability, other concerns related to project progress, photos to prove monthly work done, etc. The planning engineer/ quantity surveyor of the project is preparing the report under the guidance of the project manager. Monthly progress report will be the basis for the evaluation of monthly payment certificates in general.

A Sample Monthly Progress report is given below.




MONTHLY REPORT



FOR THE MONTH OF  JULY 2018




PROJECT PICTURE/ COVER



ANY OTHER


DATE OF SUBMSSION


------------------------------------------------------------------------------------------------------------------------

Monthly Progress Report                                                                                                                             Jan 2020


Table of Contents

1.

INTRODUCTION............................................................................................................
4

1.1.
Project Description ....................................................................................................
4

1.2.
Contract Data of the Project ....................................................................................
5

1.3.
General Description Of Monthly Progress .............................................................
6
2.

PROJECT DETAILS ......................................................................................................
7

2.1
Completion Dates for Major Activities ...................................................................
7

2.2
Project Organization ...............................................................................................
10

2.3
Construction Programme .......................................................................................
11
3.

PHYSICAL PROGRESS ..............................................................................................
12

3.1.
Work Done for Dec 2019........................................................................................
12

3.2.
Planned Work for Jan 2020 ..................................................................................
15

3.3.
Progress Photographs .............................................................................................
15
4.

FINANCIAL PROGRESS ............................................................................................
16

4.1.
Status of Financial Progress ...................................................................................
16

4.2.
Summary of Actual Work Done up to End of 2019 ....................................
17

4.3.
Physical Progress of Planned Work & Actual Work According to Cash Flow17

4.4.
Notice of Claim ........................................................................................................
17

4.5.
Variation Orders .....................................................................................................
17
5.
QUALITY ASSURANCE AND QUALITY CONTROL...........................................
18

5.1
Project Quality Plan ................................................................................................
18

5.2
Request for Information – RFI ..............................................................................
18

5.3
Shop Drawing Register ...........................................................................................
18

5.4
Design Report Register ...........................................................................................
18

5.5
Method Statement Register ....................................................................................
18

5.6
Contractor’s General Submissions – CGS ............................................................
18

5.7
Contractor’s Material Submissions – CMS ..........................................................
18

5.8
Summary of Concrete Casting ...............................................................................
18

5.9
Summary of Deliveries of Rebar ............................................................................
19

5.10    Summary of Concrete Trial Mix Test Results ..................................................
19

5.11
RICF Register ......................................................................................................
19

5.12
NCR Register .......................................................................................................
19

5.13
Bar Schedule Register .........................................................................................
19
6.
HEALTH, SAFETY, ENVIRONMENTAL AND SECURITY.................................
20

6.1
Health & Safety Key Performance Indicators ......................................................
20

6.2
Health .......................................................................................................................
21







6.3
Safety ........................................................................................................................
22

6.4
Environment ............................................................................................................
22

6.5
Security .....................................................................................................................
23
7.
CONTRACTOR'S RESOURCES...............................................................................
24

7.1.  Summary of Manpower Allocation .......................................................................
24

7.2.  Summary of Machinery Allocation .......................................................................
25
8.
Weather Record .............................................................................................................
26
9.   SITE AND OTHER MATTERS...................................................................................
26

9.1
Diary of Major Incidents During the Period ........................................................
26

9.2
Problems & Difficulties Encountered During the Period ....................................
26

9.3
Pending Matters ......................................................................................................
26
10.
LEED REPORT..........................................................................................................
26
List of Tables

Table 1: Contract data of the project .......................................................................................
5
Table 2: Completion dates for major activities ........................................................................
7
Table 3: Foreign Personnel ......................................................................................................
10
Table 4: Local Perosonnel .......................................................................................................
11
Table 5: DTP submission detail ...............................................................................................
11
Table 6: Planned and actual excavation progress ....................................................................
12
Table 7: Planned and actual D-wall hacking & capping beam casting progress .....................
14
Table 8: Status of financial progress Dec 2019 .......................................................................
16
Table 9: Summary of actual work done up to end of June 2018 .............................................
17
Table 10: Summary of Project Quality Plan submission .........................................................
18
Table 11: Health and safety key performance indicators .........................................................
20
Table 12: Anti-mosquito treatment summary table .................................................................
21
Table 13: Monthly summary of mosquito breeding control ....................................................
21


















List of Figures

Figure 1: Location of Site ..........................................................................................................
4
Figure 2: Planned and actual excavation progress ...................................................................
13
Figure 3: Planned and actual Capping Beam Casting & D-wall Hacking Progress ................
15

ANNEXTURES

Appendix A: Progress updated programme detailed time programme for July 2018
Appendix B: Programme for next month (August 2018)




1.      INTRODUCTION

1.1. Project Description

The …………… Commercial Development project located at ……….. consist of 60 – story office building. It was invested by ……………. (Pvt.) Limited and was designed by …………………… Consultants (Pvt.) Ltd.



                                                                      Figure 1: Location of Site


The project covers an area of …….. square meters and has a total building height of ………… meters. It is a super high-rise building. The podium building has a gross floor area of approximately ……….. square meters and the tower gross floor area is approximately 57000 square meters with a total gross floor area of ………. square meters.


  
1.2. Contract Data of the Project

Contract data of the project is given in the following table.

Table 1: Contract data of the project



Contract Name
:










Contract No
:

Contract Sum
:

The Employer
:










The Engineer
:










Project Architect
:







Civil and Structural Engineer
:







Services Engineer
:

Quantity Surveyor
:







Amounts of Performance bond
:




The Contractor
:










Date of Commencement
:

Scheduled date of completion
:
















Bonus Entitlement Requirement
:




Minimum Amount of Interim
:

Payment Certificate





Environmental Management and
:
Environmental Plan and Safety Plan to be prepared and
Safety Plan

monitored throughout the construction period to avoid the


environmental   pollution   in   order   to   satisfy   LEED


requirements and to ensure the safety of all the workers and


the officer engaged in the project.



Quality Assurance and Management
:
To ensure the quality of works, proper Quality Management
Plan

Plan prepared by the contractor in accordance with ISO


9001:2008 series has to be implemented on the Engineer’s


approval.









1.3. General Description of Monthly Progress

This report consists of monthly progress details of the project Main Contract Works to proposed ………………. for the period starting from …………

Summary of construction activities carried out during the reporting periods are as follows:

Tower Construction

Top Soil excavation and disposal Deep excavation in center area
Dewatering and instrumentation and monitoring Capping beam rebar works

Diaphragm wall hacking


General works and Temporary Site facilities

Construction of sanitary facilities, contractor’s site office, temporary rebar yard for capping beam rebar works and boundary wall was on progress

Surveying Works - Regular Surveying works were carried out at site



2.  PROJECT DETAILS

2.1 Completion Dates for Major Activities

Completion dates for major activities according to Detailed Time Program Rev 0.2 are given in the following table.

Table 2: Completion dates for major activities

No
Task Name
Duration
Start
Finish
1.0
Mobilization & Facilities ‐ Main Contractor
650 days
28‐Mar‐18
06‐Jan‐20
2.0
Engineering
840 days
28‐Mar‐18
14‐Jul‐20
2.1
Method Statement & Inspection Test Plans
504 days
28‐Mar‐18
13‐Aug‐19
2.2
Shop Drawings
784 days
23‐May‐18
14‐Jul‐20
2.2.1
Structural
727 days
23‐May‐18
18‐May‐20
2.2.2
Architectural
686 days
29‐Aug‐18
14‐Jul‐20
2.2.3
M&E
686 days
29‐Aug‐18
14‐Jul‐20
3.0
Procurement
869 days
31‐May‐18
15‐Oct‐20
3.1
Structural
600 days
31‐May‐18
20‐Jan‐20
3.2
Architectural
600 days
24‐Feb‐19
15‐Oct‐20
3.3
M&E
600 days
24‐Feb‐19
15‐Oct‐20
4.0
OFFICE TOWER
1096 days
28‐Mar‐18
27‐Mar‐21
4.1
Tower Crane & Passenger Hoists
187 days
31‐Oct‐18
05‐May‐19
4.2
Prerequisite Approvals
93 days
28‐Mar‐18
28‐Jun‐18
4.3
Substructure Works Tower
340 days
16‐May‐18
20‐Apr‐19
4.3.1
Excavation & Earth Works
220 days
16‐May‐18
21‐Dec‐18
4.3.2
Tower Area
211 days
08‐Aug‐18
06‐Mar‐19
4.3.3
Tower Podium
228 days
05‐Sep‐18
20‐Apr‐19
4.4
Super Structure
475 days
07‐Mar‐19
23‐Jun‐20
4.4.1
LOW ZONE
287 days
07‐Mar‐19
18‐Dec‐19
4.4.2
HIGH ZONE
191 days
16‐Dec‐19
23‐Jun‐20
4.5
Tower Architecture, MEP & ID works
646 days
25‐Apr‐19
29‐Jan‐21
4.5.1
LOW ZONE
503 days
25‐Apr‐19
08‐Sep‐20
4.5.2
HIGH ZONE
353 days
02‐Feb‐20
19‐Jan‐21
4.5.3
PH Elevation
96 days
26‐Oct‐20
29‐Jan‐21
4.6
Building Envelop
539 days
24‐Jul‐19
12‐Jan‐21
4.6.1
Elevation 1,3 & 4
439 days
24‐Jul‐19
04‐Oct‐20
4.6.2
Elevation 2 (PH Elevation)
80 days
25‐Oct‐20
12‐Jan‐21
4.7
Lifts & Escalators
247 days
18‐Apr‐20
20‐Dec‐20
4.8
Staircases
210 days
18‐Mar‐20
13‐Oct‐20
4.9
Signage
345 days
17‐Feb‐20
26‐Jan‐21
4.10
BMU
150 days
24‐Jun‐20
20‐Nov‐20
4.11
Landscape
100 days
28‐Sep‐20
05‐Jan‐21
4.12
Fire Fighting System
200 days
04‐Jul‐20
19‐Jan‐21
4.13
BMS
350 days
13‐Nov‐19
27‐Oct‐20
4.14
IT Works
350 days
13‐Nov‐19
27‐Oct‐20
4.15
Dismantle Construction Aids
42 days
05‐Oct‐20
15‐Nov‐20


2.2 Project Organization

Contractor’s project personnel are given in the following table.

Contractor's Project Personnel


Position
Name

Remarks




Project Manager



Dept Project Manager



Dept Project Manager


TBA
Commercial Manager



Chief Engineer



HSE Director



Admin Manager



QS Manager



Quantity Surveyor



Procurement officer



Finance Dept Manager



Finance Dept Assistant



M&E Manager


TBA
M&E engineer



Chief Surveyor



Surveyor



ID Manager


TBA
Material Department Manager



Construction Dept Manager



Site Engineer



QA/QC



Site Engineer



Site Engineer



HSE Manager







2.3 Construction Programme

Detailed Time Programme has been submitted for review and consent. Detailed Time Programme submission details are given in following table.

Table 5: DTP submission detail

No.

Version

Ref. No



Submitted date


Status


Date















01

Detailed Time




02-May-2019


Revise &




Programme Rev 0






Resubmit























































































3.      PHYSICAL PROGRESS


3.1. Work Done for Dec 2019 Excavation and Earth Works

Top Soil excavation up to 0.5m, deep excavation in center area and disposal along with dewatering was carried out during the reporting period. Detail of planned and actual excavation progress is given in following table.

Table 6: Planned and actual excavation progress

…………………...

………………….
………………….









Comments

Popular posts from this blog

BORED AND CAST IN SITU PILES

Bored and cast in-situ piles or bored & cast in place piles carries the process of installation in the name it self. A bored and cast in-situ pile is installed by boring the soil and or rock using heavy machinery and pouring concrete to the bored hole with or without steel reinforcement. Figure: Rotary drilling machines in the process of pile boring You can watch the detailed process in video form the following link  https://www.youtube.com/watch?v=u6YGxSzvmKo You can check more details from the following link MOS for Bored Cast In situ Pile Installation https://engcivilstuff.blogspot.com/2020/03/bored-piling-installation-by-rotary.html

MOCK UP TEST FOR LARGE CONCRETE POURS - TEMPERATURE MONITORING

                             Mass concrete is defined as "any volume of concrete with dimensions large enough to require that measures be taken to cope with the generation of heat from hydration of cement and attendant volume change to minimize cracking." [ ( ACI Committee 207–Mass and Thermally Controlled Concrete ) Mass concreting can result in high temperatures in concrete core during hydration process. Which can result thermal cracking of concrete in a severe way. Basically the temperature variance (in different locations of the concreted element) or the temperature gradient will cause the thermal cracking.

SHEET PILING

Sheet Piling is a common solution for temporary shoring work in deep excavations in the field of civil engineering. Sheet pile is a steel pile with the shape of letter C. Width, thickness, length and the shape of the sheet piles are in different categories. Normally the widths are in the range of 300mm to 700mm. And the length of the piles are normally 6m or 12m. Sample sizes of sheet piles are shown in above table.