Skip to main content

DATA SHEETS USED IN BORED CAST INSITU PILING

Boring Record in Bored Cast In-situ Piling

 Boring record is use for the recording of data during pile boring/ drilling process. Normally the recording starts from the initial setting out for temporary/ permanent casing installation based on the design coordinates of pile in layout. Start time, end time, duration, penetration rate, tools used, soil/ rock type, sample numbers, etc. are recorded in the data sheet for engineer review, by the Drilling Rig operator/ helper or by the supervisory staff. Details recording until the cleaning process of the pile bore using a cleaning bucket.

A Sample boring record sheet is shown below.


  PILING WORK FOR PROPOSED ………………………………(Project Name/ Details)
PILING WORK
CONTRACT NO :                                                                            
CLIENT             :                                                                                  CONTRACTOR :
DESIGN CONSULTANT :       
QUALITY ASSUARANCE & QUALITY CONTROLLING DOCUMENT
PILING CHECK LIST - PILE BORELOG
Check List No.:                                                                                                                         Date: 01.01.2020
Location: Block F
Drg. No.: SD -01
Block


Boring Machine Type
Rottary
Date

Model / Capacity (kNm)
BG 25
Pile No




Casing Top Level
5.51


MSL
Ground Level
5. 05


MSL
Pile Cut off Level
-1.00


MSL

Date
Time                          From    To
Tool used
Level from Casing top level (m)
Penetration Rate (mm/hr)
Torque as recorded in the Piling Rig
Sample ID
Remarks
01.01.2020
8:00
16:00
Soil auger

15
1875
-
 -

02.01.2020
16:00
18:00
Core barrel
16.5
750
-
 -
Weathered rock
02.01.2020
8:00
14:00
Core barrel
20
583
-
 -
Weathered rock

14:00
18:00
Core barrel
21.8
450
-
 -
Hard rock
03.01.2020
8:00
12:00
Core barrel
23
300
-
 -
Hard rock

12:00
14:00
Cleaning bucket


-
 -





















Comment Note :………………………………………………………………………………………………………………………
Contractor : ………………………
Engineer : ………………………
Name : ……………………………….
Name : ……………………………….
Date :  …………………………
Date :  …………………………

Comments

Popular posts from this blog

MOCK UP TEST FOR LARGE CONCRETE POURS - TEMPERATURE MONITORING

                             Mass concrete is defined as "any volume of concrete with dimensions large enough to require that measures be taken to cope with the generation of heat from hydration of cement and attendant volume change to minimize cracking." [ ( ACI Committee 207–Mass and Thermally Controlled Concrete ) Mass concreting can result in high temperatures in concrete core during hydration process. Which can result thermal cracking of concrete in a severe way. Basically the temperature variance (in different locations of the concreted element) or the temperature gradient will cause the thermal cracking.

BORED AND CAST IN SITU PILES

Bored and cast in-situ piles or bored & cast in place piles carries the process of installation in the name it self. A bored and cast in-situ pile is installed by boring the soil and or rock using heavy machinery and pouring concrete to the bored hole with or without steel reinforcement. Figure: Rotary drilling machines in the process of pile boring You can watch the detailed process in video form the following link  https://www.youtube.com/watch?v=u6YGxSzvmKo You can check more details from the following link MOS for Bored Cast In situ Pile Installation https://engcivilstuff.blogspot.com/2020/03/bored-piling-installation-by-rotary.html

BOQ FOR A GRIENFIELD TELECOMMUNICATION TOWER CONSTRUCTION

Bill of Quantities for a Tower Construction A BOQ for a telecommunication tower use for Civil Engineering works is shown in figures below. Normally in a construction of a telecommunication tower, the Civil work contractor has to undertake site clearance, access road preparation, fencing, plinths for other equipment like BTU or generators, Meter compartments if any, Foundation of tower, etc. and the installation of tower by using Rigger teams.