Main elements of a bored piling installation process
- Preliminary survey & setting out of pile point using coordinates (using Total Station)
- Driving temporary steel casing
- Pile boring (soil/ rock boring)
- Preparation of the reinforcement cage
- Cleaning or flushing pile toe
- Concreting Bored Pile
- Temporary casing extraction
- Pile Hacking
- Testing of Pile
Ground
Preparation and Setting Out
The
pile locations shall be set out in accordance with the bored pile foundation
layout plan. All setting out reference points and related contract drawings
shall also be referred. Setting out of pile location, ground level and
ancillary control points shall be checked and confirmed with the Engineer prior
to commencement of piling works. Once the first section of pile casing is
erected, the setting out with all ancillary control points and the verticality
of the pile will be re-checked with the Engineer before piling works proceeds
further.
Pre-Drilling and Driving Temporary Casing
Pre-Drilling and Driving Temporary Casing
A temporary steel casing will be driven by
casing driver attached to the boring rig or vibro-hammer if required. Before
casing driving, the alignment and verticality of the casing shall be checked to
ensure that there is no deviation from the original point.
In
cases where the maintenance for stability of borehole is difficult by drilling
fluid (SPT N<10) such as peat layer (weak layer) or in the places where
there is aggressive action of ground water and constant change of external
ground water level; permanent casing will be required to maintain the integrity
of pile shaft. In such situation case by case, situation will be informed to
engineer for further instruction.
Maximum Permitted Deviation
The
maximum permitted deviation of the pile center from the center point shown on
the setting out drawing shall be 75mm
in any direction.
Verticality
Verticality
The
maximum permitted deviation of the finished pile from the vertical is 1 in 100.
Pile Boring
with Bentonite Slurry (Wet Boring)
Boring
of the piles shall be carried out by a rotary boring rig, using special types
of boring tools depending on the soil conditions encountered. The position and
inclination of the pile have to be checked and documented. In case tolerances
are exceeded, the design engineer has to be consulted before constructing the
next neighboring pile.
The
excavated material in the bore hole is taken out by boring bucket, cleaning
bucket and the drilling fluid. The excavated material has to be documented by a
drawn borehole profile with classification of the excavated material according
to the exploration profiles. (Soil samples and Rock particles from each bore
hole shall be taken and packed in polythene bags. Bags shall be labeled with
pile reference number, depth, date of sampling etc). Especially the depth of
the surface of un-weathered rock (fresh rock) and the rock socketing shall be
documented.
Drilling Fluid
Bentonite
slurry shall be prepared at site using a mixture and stored in silos to
maintain an uninterrupted supply. The quality of the bentonite shall be checked
regularly and the results shall be recorded.
Boring Near Recently Cast Pile
Boring Near Recently Cast Pile
Piles
shall not be bored so close to other piles which have recently been cast and
which contain workable or unset concrete that a flow of concrete could be
induced from or damage caused to any of the piles. Minimum distance between two
adjacent piles which are recently casted should be 4d. According to that,
piling sequence shall be decided. A minimum period of 72 hours shall be
provided before boring near recently cast piles, unless otherwise agreed with
the Engineer.
Properties of Bentonite Slurry
Properties of Bentonite Slurry
Drilling
fluid shall be checked for following properties, during the soil boring stage
and the flushing stage of a pile.
Bentonite Slurry Properties
Property to be Measured
|
Test Method
|
Compliance values measured at 20 0C
|
|
As supplied to pile
|
Samples from pile prior to placing
concrete (Bottom)
|
||
Relative
Density
|
Mud
Density Balance
|
1.10
~ 1.15 g/ml
|
Less
than 1.25 g/ml
|
Viscosity
|
Marsh
Cone Method
|
30
to 90s
|
≤
28s
|
Sand
Percentage
|
<6%
|
≤8%
|
|
PH
value
|
PH
paper
|
7~9
|
7~9
|
In order to
check the quality of the slurry the following equipment/ tests shall be used:
- Marsh funnel
- Mud balance
- PH testing paper
Prior to
concreting of a pile, bentonite samples will be taken from the bottom of the pile
bore to test the actual properties of the bentonite slurry. A bentonite sampler
which allows collecting slurry at any depth will be lowered to pile bore in
order to collect bentonite samples. It consists of a tube and two balls on top
and bottom of the tube.
Bentonite Slurry Sampler and Working Principle
Identification
of Sound Rock Level
With
reference to the borehole logs and visual inspection of the samples obtained
from the borehole at site, sound/fresh rock identified. Inspection of samples and clarifying fresh
rock starting level shall be jointly inspected with consultant’s staff to
confirm the rock head level.
- Visual inspection of rock samples
- Penetration rate of coring rock
- Borehole data
- Boring details of adjacent piles
Termination of Drilling
When
the boring rig reaches the specified depth of socketing, the
Engineer/Engineer’s representative shall check the soil investigation
information regarding the material expected to be encountered at the approximate
level for formation of sockets and the tentative founding level of the pile
base. Boring rig shows the pile toe level by its indicators, a further check
shall be carried out at the site by dipping a tape with a plum bob attached to
the end of the tape. Pile penetration rate shall also be considered as a factor
for termination.
An
engineer/engineer representative shall inspect the borehole profiles & the
rock samples obtained from the borehole to confirm that the required depth of
the pile has been reached and boring can be terminated upon reaching rock
strata. The engineer/engineer’s representative shall be consulted to obtain
permission to terminate the drilling operations. Inspection of samples and
dipping of actual founding level shall be jointly inspected with the
engineer/engineer’s representative to confirm the condition & level of pile
base. Information for inspection as usual will be done through RIF supplemented
with direct communications with counterpart Engineer’s representative.
Preparation of the Reinforcement Cage
The
reinforcing cages will be prepared on site during the boring operation. The
reinforcing cages shall be checked to ensure that they are in accordance with
the approved construction drawings. Following parameters shall be complied with
the approved construction drawings.
Cleaning Pile Toe
Initially,
bore-hole base shall be cleaned by boring rig using cleaning bucket. If the
depth and the sand content of the bore-hole attain to satisfactory level,
concreting operation will be commenced. In case a satisfactory level is not
attained, the sediments of the pile base will be pumped out through tremie
pipes and simultaneously the pile will be filled with bentonite slurry. This
cleaning operation shall be continued until the sand content of the pile attain
to satisfactory level.
However,
after lowering the rebar cage the bore-hole will be measured and verified again
prior to concreting. If there is major soil collapse encountered, rebar cage
will be lifted up and the bore-hole will be clean again. The pile base will be
cleaned using fresh bentonite slurry circulating through trimie pipes (flushing
stage) continuously until the sand content satisfy the requirement mentioned in
table no 02.
Working sequence of pile base cleaning in flushing stage;
Working sequence of pile base cleaning in flushing stage;
Step
01 Insert reinforcement cage to
the pile.
Step
02 Insert tremie pipes to the
bore hole with attached submersible mud pump of 4” to the bottom of the tremie
pipe.
Step
03 Sediments of the pile base shall
be pumped out by submersible pump. Meanwhile bentonite will be pumped to the
borehole to maintain the bentonite head in required level.
Step 04 After attain the sand content of the
pile to satisfactory level, Bottom pump will be removed and ready the pile for
concreting.
De-Sander & Bentonite
mixer
Bentonite Handling System
Bentonite
slurry is required to stabilize the bore hole. During the drilling process
fresh bentonite is pumped to the borehole to keep it full (inside the casing
should be kept always at least 1.0m above ground water level) in order to
guarantee its stability. Prior to
concreting the bore, bentonite that is charged with particles of soil must be
cleaned or replaced. The System is made up of several components.
A leveled
area of about 40 x 20 m is required. The storage volume is substantial and is
made up of a series of tanks, silos or can be in the form of earth ponds. The system
consists of 1No.
de-sanding unit, Bentonite
mixing unit, pumps and pipelines.
Mixing
Unit
An efficient
mixing unit (fully automatic or manual operation mode) mixes bentonite powder
with water. The freshly mixed slurry is pumped to a holding and hydration tank
where the slurry is kept in motion. Hydrated bentonite slurry is then
transferred by a pump to the main reservoir / pile.
The De-sanding Unit
Bentonite Mixing Unit
The De-sanding Unit
The de-sanding
unit separates from the slurry all particles down to a cut point d50 of 60
microns and is made up of four main items: one or more hydro cyclones, driers,
distribution boxes and pumps. De-sanded slurry is pumped back to the storage
reservoir for reuse.
The Storage
Unit
De-sander
The storage
unit can be made up of a series of ponds excavated in the ground, steel tanks
stacked parallel or on top of one other or, if space is at a premium, a series
of silos. The layout can have different configurations to best suit the
geometry of the site but it is important, in order to guarantee continuity in
the work that the total capacity of storage is at least 1.5 x the volume of pile.
In the design of storage capacity, consideration should be given to the local
geology.
If there are
indications of the presence of formations that could lead to a sudden loss of
bentonite during the boring, that might be affected to the stability of the
bore hole. The size of the storage basins should take into account a surplus
supply that can be used in these emergency situations.
The Conveying Unit
The Conveying Unit
The conveying
unit is made up of a series of pumps, pipes, valves and controls designed to
facilitate conveying bentonite to and from the bore hole. On return lines,
charged slurry can have solids content higher than 8% and may need higher
pumping capacity to convey it to the de-sanding unit. The diameter of all
pipelines is normally 100 mm (4”) or 150 mm (6").
De-sanding and Bentonite testing
De-sanding and Bentonite testing
Prior to
concreting, bentonite in the bore hole must be sampled and checked to ensure
that it satisfies the minimum criteria for concreting. When this is not the
case, bentonite in the bore hole is circulated through the de-sanding plant;
alternatively it may be partly or completely replaced by fresh bentonite so
that its characteristics satisfy the contract requirements. The decision on
whether to circulate or to replace the slurry is a function of the properties
of the slurry in the bore, the contract specifications that characterize this
material, the availability of fresh bentonite and time.
Concreting
Concreting shall only commence once a sufficient number of loaded mixer trucks are available on site ready to discharge the concrete and all other trucks are confirmed for arrival. The slump of the piling concrete shall be 180 ± 25 mm before the discharge into the pile bore.
The funnel with appropriate capacity shall then be filled with concrete up to brim level. The concrete shall be released by removing the lid fixed at the bottom of the funnel and the concrete shall be discharged without interruption in one operation unit. Then the tremie pipe is raised and the concrete is placed at the bottom of the pile if needed only. Whilst concreting, the tremie pipe shall be raised in such a manner so that the embedded tremie length in to the concrete is at least 3.0 m of fresh concrete.
The concrete may be retarded to ensure that setting does not commence within four (04) hours of arrival at site. A retardation of 4 hours is recommended to avoid technical problems during concreting.
Concreting the fluid filled bore
hole is carried out using a “Tremie pipe” that introduces fresh concrete to the
bottom of the bore and allows it to rise upwards displacing the fluid in the bore
hole. Tremie pipes will be installed into the pile bore up to the pile
toe. The tremie pipes will be internally free of any old and hardened concrete
as to allow for a smooth concreting procedure. O-rings may have to be inserted
to the joints of the tremie pipes to ensure adequate water tightness.
Concreting shall only commence once a sufficient number of loaded mixer trucks are available on site ready to discharge the concrete and all other trucks are confirmed for arrival. The slump of the piling concrete shall be 180 ± 25 mm before the discharge into the pile bore.
The funnel with appropriate capacity shall then be filled with concrete up to brim level. The concrete shall be released by removing the lid fixed at the bottom of the funnel and the concrete shall be discharged without interruption in one operation unit. Then the tremie pipe is raised and the concrete is placed at the bottom of the pile if needed only. Whilst concreting, the tremie pipe shall be raised in such a manner so that the embedded tremie length in to the concrete is at least 3.0 m of fresh concrete.
The concrete may be retarded to ensure that setting does not commence within four (04) hours of arrival at site. A retardation of 4 hours is recommended to avoid technical problems during concreting.
On-site sampling and testing of
concrete usually consists of taking:
- Sets of cubes - The amount and frequency of sampling and testing
- Slump tests - carried out regularly on site to check consistency in the workability of the concrete
Concrete pouring
Concrete funnel handling using a crane
Comments
Post a Comment