Skip to main content

PRESTRESS CONCRETE

Post tensioning



 

Materials
PC Strands

 

Strands

0.50”

 

Nominal Diameter

12.7mm

 

Nominal Area

98.71mm²

 

Nominal Weight

0.775kg/m

 

Tensile Strength

1860N/mm2

 

Modulus of Elasticity

195kN/mm

 

Min Breaking Load of Strand

183.7kN

 

International Standard Used

ASTM A416

 

Sheathings
The sheathings for bonded tendons shall be spirally wound
galvanized steel tubing made from galvanized steel strips of 0.3 to
0.4mm thickness.
The sheathings shall be mortar tight to prevent entrance of
cement grout during concreting and shall be corrugated for better
bonding.
The sheathings shall be sufficiently strong to retain shapes and to
resist damages during construction.
The flat sheathings with internal width from 75mm to 90mm have
been widely used in UPS Flat anchorage systems.

 

Design data for friction / elongation calculation

 

Friction coefficient, u

:

0.2 or as per the consultant’s
recommendation

Wobble factor, k

:

0.0017/m

Stressing anchorage

:

Type FA and MA

Loss in jack and
anchorage

:

Varies from 0 ~ 2.0%

General Work Procedures

 

· Post Tensioning tendons shall be installed in accordance with
the “Approved Drawings issued for Construction”.
For Post Tensioning slabs construction
· Install bottom slab reinforcement when the slab formwork is
ready.
· Provide sufficient cover to the bottom slab reinforcement.
· Install tendons in accordance with the shop drawings.
· Install top slab reinforcement.
For Post Tensioning beams construction
· Install bottom and side reinforcements and links. No capping
links shall be installed at this stage.
· Install tendons in accordance with the shop drawings.
· Install top reinforcements and capping links of the beam.

Guidelines for Tendon Installation
· Tendon alignment shall take precedent over reinforcement.
· All dimensions measured shall be based on the formwork
level. Therefore, an accurate formwork is necessary.
· The tolerances of formwork shall be ±5mm or in accordance
with the specifications.
· The Flat Anchorages are fixed to the end formwork by
support bars to avoid any displacement during concreting.
· The Flat Anchorages must be orientated perpendicularly to
the cable axis with the grout vent at the top.
· If the side formwork is to be erected earlier, the main
contractor has to arrange for holes to be provided at the
formwork for each anchorage to accommodate protruding
strands.
· Tolerances for vertical tendon profiles are ±10mm for high
and low points.
· Tolerances for horizontal tendon profiles are ±50mm (to
avoid small M&E openings / pipes or other obstructions).
Specialist designer shall be consulted for tolerances more
than ±50mm.
· Handle ducts with care and no stepping on ducts.
· Tendon support bars and bar-chairs are placed at 1m interval
and secured with binding wire to avoid movement during
concreting.

Duct joints are sealed with tape.
· Check visually on the ducts’ straightness and do necessary
adjustment before concreting.
· Grout hoses must be protected from being embedded or
removed during concreting.

Stressing
Stressing shall not commence unless the main contractor has
confirmed the concrete of the slab / beam has achieved the
minimum cube strength at transfer. Refer to general notes of the
project.
Preparation for stressing

· Removal of the side formwork and anchorage recess former
(polyfoam).
· Placing of wedge plates and wedges. This operation must be
carried out after concreting so that the anchorages are not
fouled by grout.
· Ensure the protruding strands length is sufficient for stressing.
· The theoretical elongation calculations must be approved by
the consultant before stressing.

Cutting of Strands
commence unless the consultant has approved the stressing
result.

· Cut the protruding strands (Stressing length) to a minimum of
10mm from the wedge plate. Cutting of strand shall not
Patching of Recesses

· Remove any sand and debris from the anchorage recess.
· Mix non shrink grout or approved cementitious material with
water.
· Patch the anchorage recess with non shrink grout or approved
cementitious material using trowel until it is fully filled.

Grouting
Grouting shall not commence unless the consultant has approved
the stressing result.
Preparation for grouting

· Tendons shall be blown with compressed air to ensure no
blockage to the tendons.
Proposed grout mix
· Cement in standard 50kg package
(Ordinary Portland Cement)
· Water = 0.44 x 50kg = 22 kg
= 22 liters
· Admixture = 0.4% weight of cement (50 kg) = 200g
StoCreat AEG
Mixing sequence = water – additive – cement
Min mixing time = 3-5 min

Grouting of tendon
· Mix the grout as per approved grout mix.
· Inject grout from the tendon’s inlet hose.
· When grout flows out at the intermediate vents, lock these
vents in the direction of the grout flow.
· Lock the outlet hose when the grout flows out has the same
consistency as the grout being pumped in.
· Continue pumping to build up pressure. Lock the inlet hose
when a pressure of 3~5 bar is achieved.
· Repeat the above steps to the next tendon.

 

Safety Precautions
responsibility of the contractor.
 
Some safety measures taking at prestressing work includes, 
  • avoid standing infront of stressing tendons during stressing process

  • Use stop boads near stressing end after jack placement, to avoid cable movement in the direction of stressing
  • Proper signage to inform educate people
  • Use trained staff etc.
other than the normal safety practices in a construction site.

Comments

Popular posts from this blog

BORED AND CAST IN SITU PILES

Bored and cast in-situ piles or bored & cast in place piles carries the process of installation in the name it self. A bored and cast in-situ pile is installed by boring the soil and or rock using heavy machinery and pouring concrete to the bored hole with or without steel reinforcement. Figure: Rotary drilling machines in the process of pile boring You can watch the detailed process in video form the following link  https://www.youtube.com/watch?v=u6YGxSzvmKo You can check more details from the following link MOS for Bored Cast In situ Pile Installation https://engcivilstuff.blogspot.com/2020/03/bored-piling-installation-by-rotary.html

MOCK UP TEST FOR LARGE CONCRETE POURS - TEMPERATURE MONITORING

                             Mass concrete is defined as "any volume of concrete with dimensions large enough to require that measures be taken to cope with the generation of heat from hydration of cement and attendant volume change to minimize cracking." [ ( ACI Committee 207–Mass and Thermally Controlled Concrete ) Mass concreting can result in high temperatures in concrete core during hydration process. Which can result thermal cracking of concrete in a severe way. Basically the temperature variance (in different locations of the concreted element) or the temperature gradient will cause the thermal cracking.

SHEET PILING

Sheet Piling is a common solution for temporary shoring work in deep excavations in the field of civil engineering. Sheet pile is a steel pile with the shape of letter C. Width, thickness, length and the shape of the sheet piles are in different categories. Normally the widths are in the range of 300mm to 700mm. And the length of the piles are normally 6m or 12m. Sample sizes of sheet piles are shown in above table.